STATUS REPORT : Queensbury Lane Storm Sewer Improvements

QUEENSBURY LANE STORM SEWER 
STATUS FLASH
Project Status as of:
Friday, May 09, 2008
Accomplishments:

PROJECT IS COMPLETE.

 

 

QUEENSBURY LANE STORM SEWER 

STATUS FLASH
Project Status as of:
Monday, April 21, 2008
Accomplishments:
This will be the first project completed by the TIRZ 17.  Huff & Mitchell has replaced nearly 700 feet of storm sewer with larger 3 ft. x 5ft. box culverts to bring Queensbury Lane in compliance with the City of Houston drainage criteria. By the end of this week, crews will have completed pouring concrete over the two areas where the new, improved storm sewer connects to existing storm sewers at the frontage road of Beltway 8 and Town & Country Boulevard.

Upcoming Tasks:

Inspectors with LAN will make a final walk through to examine the completed project on Tuesday, April 21, at 10am.

QueensburyQueensbury

QUEENSBURY LANE STORM SEWER 

STATUS FLASH

Project Status as of:

Monday, April 14, 2008

Accomplishments:

A notice to proceed was issued to Huff & Mitchell (HMI) with an effective date of Monday, February 25, 2008 to commence work on the Queensbury Improvement Project. HMI mobilized on March 24, 2008. The first infrastructure project by the TIRZ-17 is near completion.  The contractor, Huff & Mitchell, has installed the larger box culverts and manholes along Queensbury between the West Sam Houston Parkway to Town & Country Boulevard.  The new and improved storm sewer was necessary to come into compliance with the City of Houston drainage criteria.

Upcoming Tasks:

The tasks for the week of April 14-19th include installing an inlet to tie-in the new storm sewer to an existing one on Town & Country Boulevard and cleaning up the area.  The project will be considered substantially complete, meaning the sewer system is fit to be used for its intended purpose.

 Queensbury Queensbury   Queensbury

QUEENSBURY LANE STORM SEWER 
STATUS FLASH
Project Status for the weeks of:
February 25, 2008 and March 3, 2008 


Accomplishments:
A preconstruction meeting in preparation for Queensbury Lane Storm Sewer Improvement Project was held at LAN on January 23, 2008. Representatives of Huff & Mitchell (Awarded Contractor), LAN, and TIRZ 17 Redevelopment Authority gathered to discuss the expectations of a successful project. An initial coordination meeting was held on February 20, 2008 with representatives from LAN, Huff & Mitchell, and contractors within the vicinity of the project limits (Burton Construction, Dyad Construction) to discuss project coordination.

Upcoming Tasks:
A Notice to Proceed was issued to Huff & Mitchell with an effective date of Monday, February 25, 2008 to commence work on the Queensbury Improvement Project. Over the next two weeks, Huff & Mitchell should provide a construction schedule to LAN. Once the construction schedule is finalized LAN will post the schedule on the TIRZ website and update regularly as needed.